PPD-MoAF: RNR Programmes and Projects Dashboard

Development Completed -- Quality Assurance and Testing For Deployment

Prototype I beta: Five Year Plan Report Management and Design From 15th Sept 2021 To 15th Dec 2021 Version 1.0 Presented on 08th April 2022
Prototype I: Change of UI/UX From 10th Jan 2022 To 11th Feb 2022 Version 1.1 Presented on 08th April 2022
Prototype II: Structuring Programmes and Activities for each Five Year Plan From 11th April 2022 To 24th April 2022 Version 1.2 Presented on 25th April 2022
Prototype III: Annual Work Plan and Projects (Crosscutting Projects/Agency wise Distribution/Flagship Programmes) From 26th April 2022 To 12th May 2022 Version 2.0 Detail Consultation on 17th May 2022
Prototype IV: Development of 4 Quadrants Reporting Dashboard From 18th May 2022 To 12th June 2022 Version 2.1 Shared for Review on 13th June 2022 and Presented on 16th June 2022
Draft Final Prototype: Integrated Feedbacks, Testing & Quality Assurance From 14th June 2022 To 20th June 2022 Version 3.0 Ready for Training & Deployment